Compliance documents by market

There is no single document pack that clears customs and the grid operator in every market. The battery can be identical; the file that proves it is not. A 100 kWh cabinet shipped to Rotterdam, to Birmingham, to Jeddah and to São Paulo needs four different sets of paperwork, and the grid-connection documents usually arrive later than the product certificates.

This index compares what each market asks for, in the order a project actually needs it: product conformity first, then safety test evidence, then grid connection, then site and fire approval. It is written for buyers and EPCs preparing an RFQ, and it is general information — not legal, electrical or fire engineering advice. Every market entry must be confirmed with the local authority having jurisdiction and the local network operator before ordering.

The four document layers, in the order they block a project

Compliance fails in stages, and each stage needs a different document from a different party. Suppliers can usually provide the first two layers. The third belongs to the grid operator and only the installer can obtain it. The fourth is the owner’s, and it is the one most often discovered late.

LayerWhat it answersWho produces itWhat buyers get wrong
1. Product conformityMay this product be placed on the market at all?Manufacturer, via a declaration of conformity and technical fileAccepting a declaration whose cited standards or model numbers do not match the unit being shipped
2. Safety test evidenceWas the specific model tested, and to which edition of which standard?Accredited test laboratory, report owned by the manufacturerAccepting a logo block instead of the report: standard edition, laboratory, report number, tested model
3. Grid connectionMay this unit export into this network at this site?Unit certificate from the manufacturer; plant certificate and application from the installer or EPCAssuming a unit certificate is a connection approval. It is one input to an application, not the approval
4. Site, fire and planningMay it be installed there, and will the insurer accept it?Installer, fire authority, building control, sometimes the insurerLeaving siting and fire strategy until after the equipment is ordered

Market comparison

The table below is a starting map, not a substitute for the market page or for local advice. Where a market has a national conformity scheme, the scheme — not the international test report — is what customs and the utility will ask to see.

MarketProduct conformitySafety test basisGrid connectionSite and fire
EUCE marking: LVD 2014/35/EU, EMC 2014/30/EU, RoHS 2011/65/EU, and Batteries Regulation (EU) 2023/1542, which is being phased in through 2027 and beyondIEC 62619 for the battery; IEC 62477-1 for the PCS; IEC 62933-5-2 for the integrated systemEN 50549-1 for low voltage, EN 50549-2 for medium voltage, then the national code of the member stateNational building and fire rules; installation safety per the IEC 62485 series
UKUKCA marking, with CE marking still accepted indefinitely for most electrical goodsBS EN IEC 62619, BS EN IEC 63056, BS EN IEC 62485-5G98 notify-and-connect at or below 16 A per phase aggregated at the premises; G99 approval above it; G100 where export is limitedBS 7671:2018+A4:2026; PAS 63100:2024 for fire siting in dwellings; planning consent for larger or protected sites
GCCCountry certificate of conformity for customs — SASO SABER in Saudi Arabia, ESMA schemes in the UAE — and the G-Mark for low-voltage equipmentIEC 62619 and IEC 62477-1 reports, usually with an accredited-body certificateUtility interconnection approval from the local distribution company, with protection settings agreed locallyCivil defence and landlord requirements; ambient temperature derating well above European assumptions
LATAMNational conformity mark where one exists — INMETRO in Brazil, RETIE in Colombia — otherwise an acceptance letterIEC 62619 and IEC 62477-1 reports, with Spanish or Portuguese documentationDistributed-generation connection process of the local utility, which differs by country and often by stateNational electrical installation code plus municipal fire approval

The EU pack is documented in detail, including which documents the supplier can issue, which the installer must obtain, and where the CE declaration stops short. The UK pack follows the same structure, including the CE and UKCA marking position and the G98 and G99 connection routes. The GCC and LATAM pages are in preparation and will follow the same structure.

The paperwork does not replace the specification. A unit that clears every document layer can still be the wrong capacity for the site, which is why the market file should sit alongside a 50–100 kWh system specification and a backup-power design rather than in place of them.

Four documents that travel everywhere

Regardless of destination, four documents are requested at the same point in every project, and asking for them in the first email rather than the week before shipment removes the most common transport delay:

  • UN38.3 test summary — required for air, sea and road transport of lithium cells and batteries. It is a test summary, not the full report, and it names the cell type.
  • Safety data sheet — the transport and handling document, in the language the freight forwarder will accept.
  • IEC 62619 report — the battery safety evidence most non-EU markets recognise as the technical basis for their own scheme.
  • IEC 62477-1 report — the power conversion safety evidence, which is frequently missing when the PCS is sourced separately from the battery.

Who is responsible for what

Most compliance disputes are not about standards; they are about which party was supposed to produce a document. Fixing that split in the contract is cheaper than discovering it during commissioning.

DocumentSupplierInstaller / EPCOwner
Declaration of conformity, test reports, UN38.3, SDSProvidesChecks scope and model matchRetains
Unit certificate for the PCSProvidesMatches it to the ordered model—
Grid connection application, protection settings, plant certificateSupports with dataObtainsSigns where the operator requires the connection party
Fire strategy, siting, building control, insurance notificationProvides test evidence on requestDesigns and submitsOwns the risk and the insurance
Import clearance and country certificateProvides the certificate originalsArranges the customs entryNamed importer of record

How to use this in an RFQ

Add one line to the RFQ: state, per destination market, which of the four layers you provide documents for, and name the document you will issue. A supplier that answers "CE and IEC available" has told you nothing about the grid application. A supplier that answers "EN 50549-1 unit certificate for the 50 kW PCS, report number and issuing body listed" has told you whether the project can be energised.

Then merge the answer with the product specification: the 12-field RFQ checklist covers the hardware, this index covers the paperwork, and the comparison worksheet turns the priced fields into one number per supplier.

Frequently asked questions

Is a CE declaration of conformity enough for an EU installation?

No. It is necessary and insufficient. The declaration covers product conformity; the installation still needs a grid-connection application to the local network operator, a plant certificate where the national code requires one, and fire and building approval from the local authority. The declaration also has to cite the right directives and the right model; a family declaration that does not name the shipped configuration is a common gap.

Can one IEC 62619 report cover several cabinet models?

Only where the report’s scope says so. Reports are written against a tested configuration and a named cell. A larger cabinet using a different module count or a different cell may fall outside that scope even when the product family is the same. Always compare the model and cell named in the report against the unit on the purchase order, and ask for the scope page rather than the cover page.

Why does the grid operator ask for documents the manufacturer has never heard of?

Because grid connection is a site-specific approval, not a product certificate. Most European operators follow a type-based process where the unit certificate covers the device and a separate plant certificate covers the as-built installation at that premises. The forms, registries and settings are national, so a certificate issued in one country does not transfer to another even where the technical standard is harmonised.

Does the destination market change the hardware?

Often yes, in three places: the grid-protection settings and firmware profile, the enclosure and thermal design for ambient temperature, and the labelling language. A unit built for a 25 °C European summer and installed where summer peaks exceed 45 °C will derate, and the warranty basis may not account for it. State the design ambient temperature in the RFQ next to the market, not in a separate email.

Need the document list checked against a real project?

Tell us the destination market and the application. We reply with the document set we would require from a supplier for that market, and what is genuinely optional.